APEGA has finished its practice review of Calgary’s 2024 feeder main break. The review found the city “had sound engineering oversight and the appropriate risk-based management in place to meet the expectations required” and no indications of unskilled practice were found. apega.ca/news/2025/05/28/apega-concludes-practice-review-on-city-of-calgary-following-2024-critical-water-main-rupture • Short URL - tr.ee/apega 👇 Part 1/2 (continued in comments) The Association of Professional Engineers and Geoscientists of Alberta (APEGA) has concluded the practice review on the City of Calgary after the critical rupture of the Bearspaw South water main in June 2024. The review was initiated on July 22, 2024, and the final report was delivered to the City of Calgary on May 7, 2025. Completion of the practice review means APEGA has assessed the city’s engineering management processes and its alignment with the Engineering and Geoscience Professions (EGP) Act, the General ...