It’s been a while since we last updated you on the East York project. Masonry is 65% complete, the roof is finished, HVAC rough-ins are 100% complete, plumbing rough-ins are 75% complete, and electrical rough-ins are approximately 40% complete. We’re aiming for framing and rough-in inspections in early March! #construction #projectmanagement #luxuryhomes #building #builder #architecture #luxurybuilder #toronto #lpdcanada #smarthome #dreamhome